Afdelingssløring forventes Q3-2024

Afdelingssløring er en udvidelse af identitessløring, som er beskrevet i målbilledet for Identitetssløring


PlantUML Macro
@startgantt

<style>
ganttDiagram {
  task {
    BackGroundColor #72BEDB
    LineColor #275F78 
    unstarted {
      BackGroundColor #FA8C6E 
      LineColor #FFAF69
    }
  }
}
</style>

' Can be daily, weekly, monthly, quartley, yearly
ganttscale weekly

'saturdays are closed
'sunday are closed


2024/07/1 to 2024/07/31 is closed

title Afdelingsslørings Gantt diagram

Project starts 2024-03-01


mainframe **Afdelingssløring opgaver **

'Milestones

[End-to-end intern test] happens 2024-06-25
[End-to-end ekstern test] happens 2024-08-11
[End-to-end ekstern test] is colored in #d20500
[Afdelingssløring i produktion] happens 2024-09-3
[Afdelingssløring ibrugtagning] happens 2024-09-17
'[SDK monolit release] happens 2024-03-12 

[ ] ends 2024-11-01


-- IDSAS --

[IDSAS 1,0,3 PROD] starts 2024/3/12
[IDSAS 1,0,3 PROD] ends 2024/9/3


--IDSAS opgaver  --


[Afdelingssløring udvikling] starts 2024/3/18
[Afdelingssløring udvikling] ends 2024/5/15

[Afdelingssløring udvikling] is 100% completed 
[Afdelingssløring udvikling] -> [IDSAS Test]


[IDSAS Test] starts 2024/5/18
[IDSAS Test] lasts 10 days
[IDSAS Test] is 100% completed

then [IDSAS 1.1.1 TEST1] lasts 15 days
[IDSAS 1.1.1 TEST1] is 100% completed

then [IDSAS 1.1.2 TEST1] lasts 15 days
[IDSAS 1.1.2 TEST1] is 15% completed

then [IDSAS 1.1.2 TEST2] lasts 30 days 
then [IDSAS 1.1.2 Prod] happens at [IDSAS 1.1.2 TEST2]'s end 
[IDSAS 1.1.2 Prod] is colored in #d20500

'[IDSAS 1.0.4 TEST1] is 0% completed
'[IDSAS 1.0.4 TEST2] is 0% completed

[IDSAS 1.1.3 PROD] starts 2024/9/3
[IDSAS 1.1.3 PROD] ends 2024/11/1


'-- Understøttende services --

'[Støtte services udvikling] starts 2024/03/18
'[Afdelingssløring udvikling] starts 0 days after [Støtte services udvikling]'s end with red dashed link
'[Støtte services udvikling] is 0% completed
'[Støtte services udvikling] requires 14 days

-- Afdelingssløring understøttes i STS --

[STS udvikling] starts 2024/3/4
[STS udvikling] ends 2024/6/5
[STS udvikling] is 100% completed

[STS udvikling] -> [STS test]

[STS test] starts 2024/6/6
[STS test] is 100% completed
[STS test] requires 8 days 
then [STS TEST1] requires 15 days 
[STS TEST1] is 25% completed
then [STS TEST2] requires 21 days
then [STS Prod] happens at [STS TEST2]'s end 
[STS Prod] is colored in #5A5A5A

-- MinLog2 --

[MinLog udvikling] starts 0 days after [STS udvikling]'s end with red dashed link  

[MinLog udvikling] starts 2024/6/16
[MinLog udvikling] requires 3 weeks
[MinLog udvikling] is 10% completed

[MinLog udvikling] -> [MinLog Test]

[MinLog Test] starts 2024/6/28
[MinLog Test] is 0% completed
then [MinLog Test] requires 15 days 
then [MinLog TEST1] requires 10 days 
then [MinLog TEST2] requires 22 days
then [MinLog Prod] happens at [MinLog TEST2]'s end 
[MinLog Prod] is colored in #d20500

'[MinLog Performances test(SDS-7101)] starts 2024/08/2
'[MinLog Performances test(SDS-7101)] requires 14 days 
'[MinLog Performances test(SDS-7101)] is Colored in orange

'-- Andre registre services --

'[Andre registre udvikling] starts 2024/4/2
'[Andre registre udvikling] requires 22 days

'[MinLog udvikling] starts 0 days after [Andre registre udvikling]'s end with red dashed link

'[Andre registre udvikling] is 0% completed


@endgantt


Identitetssløring træder i kraft marts 2024

...

Identitetssløring træder senest i kraft den 1. marts 2024 dette . Dette kan udledes af bekendtgørelse nr. 200[2] som , som er beskrevet i afsnittet Logningsbekendtgørelsen og journalføringsbekendtgørelsen.

Løsningen ibrugtages den 19. marts 2024

Projektplan for leverancer

PlantUML Macro
@startgantt

<style>
ganttDiagram {
  task {
    BackGroundColor #72BEDB
    LineColor #275F78 
    unstarted {
      BackGroundColor #FA8C6E 
      LineColor #FFAF69
    }
  }
}
</style>

' Can be daily, weekly, monthly, quartley, yearly
ganttscale weekly

'saturdays are closed
'sunday are closed

2023-12-28 to 2023/12/31 is closed
'2024/02/11 to 2024/02/18 is closed
2024/04/28 to 2024/05/1 is closed

'title Identitesslørings Gantt diagram

Project starts 2023-12-28


mainframe **IDSAS projektet for SDS**

'Milestones
[End-to-end intern test] happens 2024-02-5
[End-to-end ekstern test] happens 2024-02-21
[End-to-end ekstern test] is colored in #d20500
[Lovgivning træder i kraft] happens 2024-03-1


'[Afdelingssløring muligvis impementeret i først halvår 2024 ?] happens 2024-06-30

[SDK monolit release?] happens 2024-03-12 

'[ ] ends 2024-06-01

 --IDSAS 1.0.3  --

[IDSAS 1.0.3 Udv] starts 2024/1/25
[IDSAS 1.0.3 Udv] lasts 3 days
[IDSAS 1.0.3 Udv] is 100% completed 

[IDSAS 1.0.3 QA] starts 2024/1/25
[IDSAS 1.0.3 QA] lasts 1 days
[IDSAS 1.0.3 QA] is 100% completed

[IDSAS 1.0.3 TEST1] starts 2024/1/26 
'[IDSAS 1.0.3 TEST1] is 22% completed  
[IDSAS 1.0.3 TEST1] lasts 140 days
[IDSAS 1.0.3 TEST2] starts 2024/2/2 
'[IDSAS 1.0.3 TEST2] is 18% completed    

[IDSAS 1.0.3 TEST2] lasts 140 days 
[IDSAS 1.0.3 Prod] happens at 2024/3/1
[IDSAS 1.0.3 Prod] is colored in #d20500
 




-- STS --

[STS Udvikling] starts 2024/1/1
[STS Udvikling] lasts 25 days  
[STS Udvikling] is 100% completed
[STS QA] starts 2024/1/3
[STS QA] lasts 23 days  
[STS QA] is 100% completed

[STS TEST1] starts 2024/1/26 
[STS QA] is 100% completed
[STS TEST1] lasts 140 days 
[STS TEST2] starts 2024/2/5
[STS TEST2] lasts 140 days

[STS Prod] happens at 2024/3/4
[STS Prod] is colored in #d20500
'[STS TEST1] is 22% completed
'[STS TEST2] is 14% completed

'[STS Performances test] starts 2024/02/18
'[STS Performances test] lasts 10 days 
'[STS Performances test] is Colored in red


-- MinLog2 --

[MinLog udv] starts 2024/1/1



[MinLog udv] lasts 34 days 
[MinLog QA] lasts 3 days 
[MinLog QA] starts 2024/02/05
[MinLog TEST1] starts 2024/02/06
[MinLog TEST1] lasts 140 days 
'[MinLog TEST1] is 14% completed

[MinLog TEST2] starts 2024/02/12
[MinLog TEST2] lasts 140 days
'[MinLog TEST2] is 10% completed

[MinLog Prod] happens at 2024/03/04
'[MinLog Prod] las
[MinLog Prod] is colored in #d20500


[MinLog udv] is 100% completed
[MinLog QA] is 100% completed


@endgantt



Som projektet skrider frem, vil der løbende blive offentliggjort forventninger til tidsplanen for IDSAS-Som projektet forløber vil der her løbende blive offentlig gjort forventninger til tidsplan for IDSAS komponenten, relaterede services og miljøer.

Forventet/ ca. datokomponent

Test1

Test2

Produktion

I brugtagning

Ultimo januar 2024MinLog LookupID med IDSAS understøttelse TEST1
ultimo feb 20244. marts19. marts 2024
Ultimo
Medio
januar 2024Identitestsløringsservice v. 1.0.326. januar 20242. feb 20241
TEST1
. marts19. marts 2024
Medio januar 2024STS med IDSAS understøttelse borgerspecifik sløring 2.8
.3X
.4026. januar 20245. feb 20244. marts19. marts 2024
Ultimo januar 2024Identitestsløringsservice v. 1.0.225. januar 2024--
Medio januar 2024Identitestsløringsservice v. 1.0.1.118. januar 2024-
TEST1


December 2023Identitestsløringsservice v. 1.0.014. december 2023

5. januar 2024

-
NovemberRC frigivet - Identitestsløringsservice 1.0.0 - rc.813. november 2023


AugustFørste RC frigivet - Identitestsløringsservice 1.0.0 - rc.622. august 2023


  1. marts 2023
Udvikling af komponenter til oprettelse af sløring mm.-


  1. juni 2022
Identitessløringsprojektet i gang sat-