Afdelingssløring er en udvidelse af identitessløring, som er beskrevet i målbilledet for Identitetssløring
@startgantt <style> ganttDiagram { task { BackGroundColor #72BEDB LineColor #275F78 unstarted { BackGroundColor #FA8C6E LineColor #FFAF69 } } } </style> ' Can be daily, weekly, monthly, quartley, yearly ganttscale weekly 'saturdays are closed 'sunday are closed 2024/07/1 to 2024/07/31 is closed title Afdelingsslørings Gantt diagram Project starts 2024-03-01 mainframe **Afdelingssløring opgaver ** 'Milestones [End-to-end intern test] happens 2024-06-22 [End-to-end ekstern test] happens 2024-08-11 [End-to-end ekstern test] is colored in #d20500 [Afdelingssløring i produktion] happens 2024-09-3 [Afdelingssløring ibrugtagning] happens 2024-09-17 '[SDK monolit release] happens 2024-03-12 [ ] ends 2024-11-01 -- IDSAS -- [IDSAS 1,0,3 PROD] starts 2024/3/12 [IDSAS 1,0,3 PROD] ends 2024/9/3 --IDSAS opgaver -- [Afdelingssløring udvikling] starts 2024/3/18 [Afdelingssløring udvikling] ends 2024/5/15 [Afdelingssløring udvikling] is 95% completed [Afdelingssløring udvikling] -> [IDSAS Test] [IDSAS Test] starts 2024/5/18 [IDSAS Test] lasts 20 days [IDSAS Test] is 0% completed then [IDSAS 1.0.4 TEST1] lasts 21 days then [IDSAS 1.0.4 TEST2] lasts 30 days then [IDSAS 1.0.4 Prod] happens at [IDSAS 1.0.4 TEST2]'s end [IDSAS 1.0.4 Prod] is colored in #d20500 '[IDSAS 1.0.4 TEST1] is 0% completed '[IDSAS 1.0.4 TEST2] is 0% completed [IDSAS 1,0,4 PROD] starts 2024/9/3 [IDSAS 1,0,4 PROD] ends 2024/11/1 '-- Understøttende services -- '[Støtte services udvikling] starts 2024/03/18 '[Afdelingssløring udvikling] starts 0 days after [Støtte services udvikling]'s end with red dashed link '[Støtte services udvikling] is 0% completed '[Støtte services udvikling] requires 14 days -- Afdelingssløring understøttes i STS -- [STS udvikling] starts 2024/3/4 [STS udvikling] ends 2024/5/16 [STS udvikling] is 65% completed [STS udvikling] -> [STS test] [STS test] starts 2024/5/17 [STS test] is 0% completed [STS test] requires 25 days then [STS TEST1] requires 21 days then [STS TEST2] requires 21 days then [STS Prod] happens at [STS TEST2]'s end [STS Prod] is colored in #5A5A5A -- MinLog2 -- [MinLog udvikling] starts 0 days after [STS udvikling]'s end with red dashed link [MinLog udvikling] starts 2024/5/16 [MinLog udvikling] requires 4 weeks [MinLog udvikling] is 0% completed [MinLog udvikling] -> [MinLog Test] [MinLog Test] starts 2024/6/2 [MinLog Test] is 0% completed then [MinLog Test] requires 16 days then [MinLog TEST1] requires 14 days then [MinLog TEST2] requires 28 days then [MinLog Prod] happens at [MinLog TEST2]'s end [MinLog Prod] is colored in #d20500 '[MinLog Performances test(SDS-7101)] starts 2024/08/2 '[MinLog Performances test(SDS-7101)] requires 14 days '[MinLog Performances test(SDS-7101)] is Colored in orange '-- Andre registre services -- '[Andre registre udvikling] starts 2024/4/2 '[Andre registre udvikling] requires 22 days '[MinLog udvikling] starts 0 days after [Andre registre udvikling]'s end with red dashed link '[Andre registre udvikling] is 0% completed @endgantt |
Identitetssløring træder senest i kraft den 1. marts 2024. Dette kan udledes af bekendtgørelse, som er beskrevet i afsnittet Logningsbekendtgørelsen og journalføringsbekendtgørelsen.
Løsningen ibrugtages den 19. marts 2024
@startgantt <style> ganttDiagram { task { BackGroundColor #72BEDB LineColor #275F78 unstarted { BackGroundColor #FA8C6E LineColor #FFAF69 } } } </style> ' Can be daily, weekly, monthly, quartley, yearly ganttscale weekly 'saturdays are closed 'sunday are closed 2023-12-28 to 2023/12/31 is closed '2024/02/11 to 2024/02/18 is closed 2024/04/28 to 2024/05/1 is closed 'title Identitesslørings Gantt diagram Project starts 2023-12-28 mainframe **IDSAS projektet for SDS** 'Milestones [End-to-end intern test] happens 2024-02-5 [End-to-end ekstern test] happens 2024-02-21 [End-to-end ekstern test] is colored in #d20500 [Lovgivning træder i kraft] happens 2024-03-1 '[Afdelingssløring muligvis impementeret i først halvår 2024 ?] happens 2024-06-30 [SDK monolit release?] happens 2024-03-12 '[ ] ends 2024-06-01 --IDSAS 1.0.3 -- [IDSAS 1.0.3 Udv] starts 2024/1/25 [IDSAS 1.0.3 Udv] lasts 3 days [IDSAS 1.0.3 Udv] is 100% completed [IDSAS 1.0.3 QA] starts 2024/1/25 [IDSAS 1.0.3 QA] lasts 1 days [IDSAS 1.0.3 QA] is 100% completed [IDSAS 1.0.3 TEST1] starts 2024/1/26 '[IDSAS 1.0.3 TEST1] is 22% completed [IDSAS 1.0.3 TEST1] lasts 140 days [IDSAS 1.0.3 TEST2] starts 2024/2/2 '[IDSAS 1.0.3 TEST2] is 18% completed [IDSAS 1.0.3 TEST2] lasts 140 days [IDSAS 1.0.3 Prod] happens at 2024/3/1 [IDSAS 1.0.3 Prod] is colored in #d20500 -- STS -- [STS Udvikling] starts 2024/1/1 [STS Udvikling] lasts 25 days [STS Udvikling] is 100% completed [STS QA] starts 2024/1/3 [STS QA] lasts 23 days [STS QA] is 100% completed [STS TEST1] starts 2024/1/26 [STS QA] is 100% completed [STS TEST1] lasts 140 days [STS TEST2] starts 2024/2/5 [STS TEST2] lasts 140 days [STS Prod] happens at 2024/3/4 [STS Prod] is colored in #d20500 '[STS TEST1] is 22% completed '[STS TEST2] is 14% completed '[STS Performances test] starts 2024/02/18 '[STS Performances test] lasts 10 days '[STS Performances test] is Colored in red -- MinLog2 -- [MinLog udv] starts 2024/1/1 [MinLog udv] lasts 34 days [MinLog QA] lasts 3 days [MinLog QA] starts 2024/02/05 [MinLog TEST1] starts 2024/02/06 [MinLog TEST1] lasts 140 days '[MinLog TEST1] is 14% completed [MinLog TEST2] starts 2024/02/12 [MinLog TEST2] lasts 140 days '[MinLog TEST2] is 10% completed [MinLog Prod] happens at 2024/03/04 '[MinLog Prod] las [MinLog Prod] is colored in #d20500 [MinLog udv] is 100% completed [MinLog QA] is 100% completed @endgantt |
Som projektet skrider frem, vil der løbende blive offentliggjort forventninger til tidsplanen for IDSAS-komponenten, relaterede services og miljøer.
Forventet/ ca. dato | komponent | Test1 | Test2 | Produktion | I brugtagning |
---|---|---|---|---|---|
Ultimo januar 2024 | MinLog LookupID med IDSAS understøttelse | TEST1 | ultimo feb 2024 | 4. marts | 19. marts 2024 |
Ultimo januar 2024 | Identitestsløringsservice v. 1.0.3 | 26. januar 2024 | 2. feb 2024 | 1. marts | 19. marts 2024 |
Medio januar 2024 | STS med IDSAS understøttelse borgerspecifik sløring 2.8.40 | 26. januar 2024 | 5. feb 2024 | 4. marts | 19. marts 2024 |
Ultimo januar 2024 | Identitestsløringsservice v. 1.0.2 | 25. januar 2024 | - | - | |
Medio januar 2024 | Identitestsløringsservice v. 1.0.1.1 | 18. januar 2024 | - | ||
December 2023 | Identitestsløringsservice v. 1.0.0 | 14. december 2023 | 5. januar 2024 | - | |
November | RC frigivet - Identitestsløringsservice 1.0.0 - rc.8 | 13. november 2023 | |||
August | Første RC frigivet - Identitestsløringsservice 1.0.0 - rc.6 | 22. august 2023 | |||
| Udvikling af komponenter til oprettelse af sløring mm. | - | |||
| Identitessløringsprojektet i gang sat | - |