@startgantt Project starts 2025-03-01 printscale weekly 2025-04-14 to 2025-04-21 is closed 2025-04-14 to 2025-04-21 are named [Påske] 2025-04-14 to 2025-04-21 are colored in salmon 2025-06-30 to 2025-07-20 is closed 2025-06-30 to 2025-07-20 are named [Sommerferie] 2025-06-30 to 2025-07-20 are colored in salmon
2025-10-13 to 2025-10-19 is closed 2025-10-13 to 2025-10-19 are named [Efterårsferie] 2025-10-13 to 2025-10-19 are colored in salmon
-- Projektopgaver -- [Research og Specifikation] requires 8 weeks [Arkitektur Kickoff] happens on 2025-04-03 [Informationssikkerhedsanalyse] starts on 2025-06-02 and requires 2 weeks -- Eksterne udviklingsforløb -- [EDI Portal udvikling API] starts on 2025-06-01 and requires 5 weeks [EDI Portal udvikling UX] starts at [EDI Portal udvikling API]'s end and requires 6 weeks [EDI Portal udvikling UX] starts after [Sommerferie]'s end [Sundhed.dk DDTV UX] starts on 2025-05-01 and requires 6 weeks [Sundhed.dk udvikling og intern test] starts at [Sundhed.dk DDTV UX]'s end and requires 14 weeks [DigPost i Test1] happens on 2025-07-01 [DigPost i Test2] happens on 2025-09-01 -- Udviklingsforløb -- [Udvikling Kickoff] happens on 2025-04-30 [NSP IDWS service] starts 2 days after [Udvikling Kickoff]'s end and requires 6 weeks [QA1] happens 2 weeks after [Udvikling Kickoff]'s end [QA2] happens 2 weeks after [QA1]'s end [QA3] happens 2 weeks after [QA2]'s end [QA2] displays on same row as [QA1] [QA3] displays on same row as [QA1] [NSP DGWS service] starts at [NSP IDWS service]'s end and requires 4 weeks [QA4] happens at [NSP DGWS service]'s start [QA5] happens 2 weeks after [QA4]'s end [QA6] happens 2 weeks after [QA5]'s end [QA5] displays on same row as [QA4] [QA6] displays on same row as [QA4] [NSP Job udvikling] starts at [NSP IDWS service]'s end and requires 9 weeks [QA7] happens at [NSP Job udvikling]'s start [QA8] happens 2 weeks after [QA7]'s end [QA9] happens on 2025-08-21 [QA10] happens on 2025-08-21 [RC deploy] happens on 2025-09-10 [RC 0.3 deploy] happens on 2025-09-26 [QA8] displays on same row as [QA7] [QA9] displays on same row as [QA7] [RC deploy] displays on same row as [QA7] [RC 0.3 deploy] displays on same row as [QA7] -- QA Forløb -- [Final QA (IDWS)] starts 1 days after [RC 0.3 deploy]'s end and requires 2 weeks [Final QA (DGWS)] starts 1 days after [RC 0.3 deploy]'s end and requires 2 weeks [Final QA (Jobs)] starts 1 days after [RC 0.3 deploy]'s end and requires 2 weeks [Option: Performancetest] starts after [Efterårsferie]'s end and requires 2 weeks -- Tilgængelighed i NSP test -- [IDWS service på Test1] happens on 2025-07-11 [IDWS service på Test2] happens 1 weeks after [Final QA (IDWS)]'s end [Final QA (IDWS)] -> [IDWS service på Test2] [DGWS service på Test1] happens on 2025-08-01 [DGWS service på Test2] happens 1 weeks after [Final QA (DGWS)]'s end [Final QA (DGWS)] -> [DGWS service på Test2] [Jobs på Test1] happens 1 weeks after [RC deploy]'s end [Jobs på Test2] happens 1 weeks after [Final QA (Jobs)]'s end [Final QA (Jobs)] -> [Jobs på Test2] -- Hul igennem og End-2-End Test -- [Hul igennem test] starts 1 days after [Jobs på Test2]'s end and requires 1 week [Jobs på Test2] -> [Hul igennem test] [EDI Portal udvikling UX] -> [Hul igennem test] [Sundhed.dk udvikling og intern test] -> [Hul igennem test] [End-2-End test planlægning] starts on 2025-09-01 and requires 5 weeks [End-2-End test] starts on 2025-11-24 and requires 2 weeks [End-2-End test planlægning] -> [End-2-End test]
-- Drift og Ibrugtagning -- [DDTV produktionsigangsætning] starts 6 weeks after [Jobs på Test2]'s end and requires 3 weeks [DDTV klar til ibrugtagning] happens on 2026-01-01 @endgantt
|