@startgantt
Project starts 2025-03-01
printscale weekly

2025-04-14 to 2025-04-21 is closed
2025-04-14 to 2025-04-21 are named [Påske]
2025-04-14 to 2025-04-21 are colored in salmon
2025-07-14 to 2025-08-03 is closed
2025-07-14 to 2025-08-03 are named [Sommerferie]
2025-07-14 to 2025-08-03 are colored in salmon
2025-10-13 to 2025-10-19 is closed
2025-10-13 to 2025-10-19 are named [Efterårsferie]
2025-10-13 to 2025-10-19 are colored in salmon

-- Projektopgaver --
[Research og Specifikation] requires 8 weeks
[Arkitektur Kickoff] happens on 2025-04-03
[Sikkerhedsanalyse] starts on 2025-06-02 and requires 2 weeks

-- Udviklingsforløb --
[Udvikling Kickoff] happens on 2025-04-30
[NSP OIO-IDWS service] starts 2 days after [Udvikling Kickoff]'s end and requires 6 weeks
[QA1] happens 2 weeks after [Udvikling Kickoff]'s end
[QA2] happens 2 weeks after [QA1]'s end
[QA3] happens 2 weeks after [QA2]'s end
[QA2] displays on same row as [QA1]
[QA3] displays on same row as [QA1]

[DDTV Job udvikling] starts at [NSP OIO-IDWS service]'s end and requires 4 weeks
[QA4] happens at [DDTV Job udvikling]'s start
[QA5] happens 2 weeks after [QA4]'s end
[QA6] happens 2 weeks after [QA5]'s end
[QA5] displays on same row as [QA4]
[QA6] displays on same row as [QA4]

[NSP DGWS udvikling] starts at [DDTV Job udvikling]'s end and requires 4 weeks
[NSP DGWS udvikling] starts after [Sommerferie]'s end
[QA7] happens at [NSP DGWS udvikling]'s start
[QA8] happens 2 weeks after [QA7]'s end
[QA9] happens 2 weeks after [QA8]'s end
[QA8] displays on same row as [QA7]
[QA9] displays on same row as [QA7]

-- QA Forløb --
[QA-forløb (OIO-IDWS service)] requires 2 weeks
[QA-forløb (OIO-IDWS service)] starts after [NSP OIO-IDWS service]'s end

[QA-forløb (jobs)] requires 2 weeks
[QA-forløb (jobs)] starts after [NSP DGWS udvikling]'s end
[QA-forløb (jobs)] starts after [Sommerferie]'s end

[QA-forløb (DGWS service)] requires 2 weeks
[QA-forløb (DGWS service)] starts after [NSP DGWS udvikling]'s end

[Option: Performancetest] starts after [Efterårsferie]'s end and requires 2 weeks

-- Tilgængelighed i NSP test --
[OIO-IDWS service i Test1] happens 2 weeks after [QA-forløb (OIO-IDWS service)]'s end
[QA-forløb (OIO-IDWS service)] -> [OIO-IDWS service i Test1]
[OIO-IDWS service i Test2] happens 2 weeks after [OIO-IDWS service i Test1]'s end
[OIO-IDWS service i Test1] -> [OIO-IDWS service i Test2]
[OIO-IDWS service i Test2] happens 2 week after [Sommerferie]'s end

[Jobs på Test1] happens 2 weeks after [QA-forløb (jobs)]'s end
[QA-forløb (jobs)] -> [Jobs på Test1]
[Jobs på Test1] happens 2 weeks after [Sommerferie]'s end
[Jobs på Test2] happens 2 weeks after [Jobs på Test1]'s end
[Jobs på Test1] -> [Jobs på Test2]

[DGWS service på Test1] happens 2 weeks after [QA-forløb (DGWS service)]'s end
[DGWS service på Test1] happens 2 weeks after [Jobs på Test1]'s end
[DGWS service på Test2] happens 2 weeks after [DGWS service på Test1]'s end
[DGWS service på Test1] -> [DGWS service på Test2]

-- Drift og Ibrugtagning --
[DDTV produktionsigangsætning] starts 4 weeks after [DGWS service på Test2]'s end and requires 3 weeks
[DDTV klar til ibrugtagning] happens 1 week after [DDTV produktionsigangsætning]'s end
@endgantt