@startgantt
Project starts 2025-03-01 printscale weekly
2025-04-14 to 2025-04-21 is closed 2025-04-14 to 2025-04-21 are named [Påske]
2025-04-14 to 2025-04-21 are colored in salmon 2025-07-14 to 2025-08-03 is closed 2025-07-14 to 2025-08-03 are named [Sommerferie] 2025-07-14 to 2025-08-03 are colored in salmon 2025-10-13 to 2025-10-19 is closed 2025-10-13 to 2025-10-19 are named [Efterårsferie] 2025-10-13 to 2025-10-19 are colored in salmon
-- Projektopgaver --
[Research og Specifikation] requires 8 weeks [Arkitektur Kickoff] happens on 2025-04-03 [Sikkerhedsanalyse] starts on 2025-06-02 and requires 2 weeks
-- Udviklingsforløb -- [Udvikling Kickoff] happens on 2025-04-28 [NSP service] starts 2 days after [Udvikling Kickoff]'s end and requires 6 weeks [QA1] happens 2 weeks after [Udvikling Kickoff]'s end [QA2] happens 2 weeks after [QA1]'s end [QA3] happens 2 weeks after [QA2]'s end [QA2] displays on same row as [QA1] [QA3] displays on same row as [QA1]
[DDTV Kø udvikling] starts at [NSP service]'s end and requires 4 weeks [QA4] happens at [DDTV Kø udvikling]'s start [QA5] happens 2 weeks after [QA4]'s end [QA6] happens 2 weeks after [QA5]'s end [QA5] displays on same row as [QA4] [QA6] displays on same row as [QA4]
[DDTV Webserver udvikling] starts at [DDTV Kø udvikling]'s end and requires 4 weeks [DDTV Webserver udvikling] starts after [Sommerferie]'s end [QA7] happens at [DDTV Webserver udvikling]'s start [QA8] happens 2 weeks after [QA7]'s end [QA9] happens 2 weeks after [QA8]'s end [QA8] displays on same row as [QA7] [QA9] displays on same row as [QA7]
-- QA Forløb -- [QA-forløb (service)] requires 2 weeks [QA-forløb (service)] starts after [NSP service]'s end
[QA-forløb (kø)] requires 2 weeks [QA-forløb (kø)] starts after [DDTV Webserver udvikling]'s end [QA-forløb (kø)] starts after [Sommerferie]'s end
[QA-forløb (Web server)] requires 2 weeks [QA-forløb (Web server)] starts after [DDTV Webserver udvikling]'s end
[Option: Performancetest] starts after [Efterårsferie]'s end and requires 2 weeks
-- Tilgængelighed i NSP test -- [NSP service i Test1] happens 2 weeks after [QA3]'s end [QA1] -> [NSP service i Test1] [NSP service i Test2] happens 2 weeks after [NSP service i Test1]'s end [NSP service i Test1] -> [NSP service i Test2] [NSP service i Test2] happens 2 week after [Sommerferie]'s end
[Kømekanisme i Test1] happens 2 weeks after [QA2]'s end [QA2] -> [Kømekanisme i Test1] [Kømekanisme i Test1] happens 2 weeks after [QA6]'s end [Kømekanisme i Test2] happens 2 weeks after [Kømekanisme i Test1]'s end [Kømekanisme i Test1] -> [Kømekanisme i Test2]
[Webserver i Test1] happens 2 weeks after [QA3]'s end [Webserver i Test1] happens 2 weeks after [Kømekanisme i Test1]'s end [Webserver i Test2] happens 2 weeks after [Webserver i Test1]'s end [Webserver i Test1] -> [Webserver i Test2]
-- Drift og Ibrugtagning -- [DDTV produktionsigangsætning] starts 4 weeks after [Webserver i Test2]'s end and requires 3 weeks [DDTV klar til ibrugtagning] happens 1 week after [DDTV produktionsigangsætning]'s end
@endgantt |