@startgantt
Project starts 2025-03-01
printscale weekly
2025-04-14 to 2025-04-21 is closed
2025-04-14 to 2025-04-21 are named [Påske] 2025-04-14 to 2025-04-21 are colored in salmon
2025-07-14 to 2025-08-03 is closed
2025-07-14 to 2025-08-03 are named [Sommerferie]
2025-07-14 to 2025-08-03 are colored in salmon
2025-10-13 to 2025-10-19 is closed
2025-10-13 to 2025-10-19 are named [Efterårsferie]
2025-10-13 to 2025-10-19 are colored in salmon [Research og Specifikation] as [RD] requires 8 weeks
[Arkitektur Kickoff] as [M1] happens on 2025-04-03
-- Udviklingsforløb --
[Udvikling Kickoff] happens on 2025-04-28
[NSP service] starts 2 days after [Udvikling Kickoff]'s end and requires 6 weeks
[DDTV Kø udvikling] starts at [NSP service]'s end and requires 4 weeks
[DDTV Webserver udvikling] starts at [DDTV Kø udvikling]'s end and requires 4 weeks
[DDTV Webserver udvikling] starts after [Sommerferie]'s end
-- QA Forløb --
[QA1 (service)] as [QA1] requires 2 weeks
[QA1] starts after [NSP service]'s end

[QA2 (kø)] as [QA2] requires 2 weeks
[QA2] starts after [DDTV Kø udvikling]'s end
[QA2] starts after [Sommerferie]'s end

[QA3 (Web server)] as [QA3] requires 1 week
[QA3] starts after [DDTV Webserver udvikling]'s end
[Option: Performancetest] starts after [Efterårsferie] and requires 2 weeks
-- Tilgængelighed i NSP test --
[NSP service i Test1] happens 2 weeks after [QA1]'s end
[QA1] -> [NSP service i Test1]
[NSP service i Test2] happens 2 weeks after [NSP service i Test1]'s end
[NSP service i Test1] -> [NSP service i Test2]
[NSP service i Test2] happens 2 week after [Sommerferie]'s end

[Kømekanisme i Test1] happens 2 weeks after [QA2]'s end
[QA2] -> [Kømekanisme i Test1]
[Kømekanisme i Test1] happens 2 weeks after [NSP service i Test1]'s end
[Kømekanisme i Test2] happens 2 weeks after [Kømekanisme i Test1]'s end
[Kømekanisme i Test1] -> [Kømekanisme i Test2]
[Webserver i Test1] happens 2 weeks after [QA3]'s end
[Webserver i Test1] happens 2 weeks after [Kømekanisme i Test1]'s end
[Webserver i Test2] happens 2 weeks after [Webserver i Test1]'s end
[Webserver i Test1] -> [Webserver i Test2]
-- Drift og Ibrugtagning --
[DDTV produktionsigangsætning] starts 4 weeks after [Webserver i Test2]'s end and requires 3 weeks
[DDTV klar til ibrugtagning] happens 1 week after [DDTV produktionsigangsætning]'s end @endgantt