@startgantt
Project starts 2025-03-01 printscale weekly
2025-04-14 to 2025-04-21 is closed 2025-04-14 to 2025-04-21 are named [Påske]
2025-04-14 to 2025-04-21 are colored in salmon 2025-07-14 to 2025-08-03 is closed 2025-07-14 to 2025-08-03 are named [Sommerferie] 2025-07-14 to 2025-08-03 are colored in salmon 2025-10-13 to 2025-10-19 is closed 2025-10-13 to 2025-10-19 are named [Efterårsferie] 2025-10-13 to 2025-10-19 are colored in salmon
[Research og Specifikation] as [RD] requires 8 weeks [Arkitektur Kickoff] as [M1] happens on 2025-04-03 -- Udviklingsforløb -- [Udvikling Kickoff] happens on 2025-04-28 [NSP service] starts 2 days after [Udvikling Kickoff]'s end and requires 6 weeks [DDTV Kø udvikling] starts at [NSP service]'s end and requires 4 weeks [DDTV Webserver udvikling] starts at [DDTV Kø udvikling]'s end and requires 4 weeks -- QA Forløb -- [QA1 (service)] as [QA1] requires 2 weeks [QA1] starts 3 days after [NSP service]'s end [QA2 (kø)] as [QA2] requires 2 weeks [QA2] starts 3 days after [DDTV Kø udvikling]'s end [QA3 (Web server)] as [QA3] requires 1 week [QA3] starts 3 days after [DDTV Webserver udvikling]'s end -- Tilgængelighed i NSP test -- [NSP service i Test1] happens 2 weeks after [QA1]'s end [NSP service i Test2] happens 2 weeks after [NSP service i Test1]'s end [NSP service i Test2] happens 2 week after [Sommerferie]'s end [Kømekanisme i Test1] happens 2 weeks after [QA2]'s end [Kømekanisme i Test1] happens 2 weeks after [NSP service i Test1]'s end [Kømekanisme i Test2] happens 2 weeks after [Kømekanisme i Test1]'s end
[Webserver i Test1] happens 2 weeks after [QA3]'s end [Webserver i Test1] happens 2 weeks after [Kømekanisme i Test1]'s end [Webserver i Test2] happens 2 weeks after [Webserver i Test1]'s end
@endgantt |