@startgantt
Project starts 2025-03-01 printscale weekly
2025-04-14 to 2025-04-21 is closed 2025-04-14 to 2025-04-21 are named [Påske]
2025-04-14 to 2025-04-21 are colored in salmon 2025-07-14 to 2025-08-03 is closed 2025-07-14 to 2025-08-03 are named [Sommerferie] 2025-07-14 to 2025-08-03 are colored in salmon
[Research og Specifikation] as [RD] requires 8 weeks [Arkitektur Kickoff] as [M1] happens on 2025-04-03 -- Udviklingsforløb -- [Udvikling Kickoff] as [M2] happens on 2025-04-28 [DDTV NSP Service udvikling] as [NSP] requires 6 weeks [NSP] starts 2 days after [M2]'s end [DDTV Kø udvikling] as [Q] requires 4 weeks [Q] starts 2 weeks after [NSP]'s start [DDTV Webserver udvikling] as [WS] requires 4 weeks [Q] -> [WS] -- QA Forløb -- [QA1 (service)] as [QA1] requires 2 weeks [QA1] starts 3 days after [NSP]'s end [QA2 (kø)] as [QA2] requires 2 weeks
@endgantt |