@startgantt
Project starts 2025-03-01
printscale weekly
2025-04-14 to 2025-04-21 is closed
2025-04-14 to 2025-04-21 are named [Påske] 2025-04-14 to 2025-04-21 are colored in salmon
2025-07-14 to 2025-08-03 is closed
2025-07-14 to 2025-08-03 are named [Sommerferie]
2025-07-14 to 2025-08-03 are colored in salmon
[Research og Specifikation] as [RD] requires 8 weeks
[Arkitektur Kickoff] as [M1] happens on 2025-04-03
-- Udviklingsforløb --
[Udvikling Kickoff] as [M2] happens on 2025-04-28
[DDTV NSP Service udvikling] as [Sprint12] requires 6 weeks
[Sprint12] starts 2 days after [M2]'s end
[DDTV Kø udvikling] as [Q] requires 4 weeks
[Q] starts 2 weeks after [Sprint12]'s start
[DDTV Webserver udvikling] as [WS] requires 4 weeks
[Q] -> [WS]
-- QA Forløb --
[Service og Kø QA og rettelser] as [QA1] requires 3 weeks
[QA1] starts 1 week after [Q]'s end
[Intern Test] as [IntT] requires 1 week
[IntT] starts on 2025-08-04
[Klar til QA] happens 3 days after [IntT]'s end @endgantt