Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
PlantUML Render Macro

@startgantt
Project starts 2025-03-01
printscale weekly

2025-04-14 to 2025-04-21 is closed
2025-04-14 to 2025-04-21 are named [Påske]
2025-04-14 to 2025-04-21 are colored in salmon


2025-06-30 to 2025-07-20 is closed
2025-06-30 to 2025-07-20 are named [Sommerferie]
2025-06-30 to 2025-07-20 are colored in salmon


2025-10-13 to 2025-10-19 is closed
2025-10-13 to 2025-10-19 are named [Efterårsferie]
2025-10-13 to 2025-10-19 are colored in salmon

-- Projektopgaver --
[Research og Specifikation] requires 8 weeks
[Arkitektur Kickoff] happens on 2025-04-03
[Informationssikkerhedsanalyse] starts on 2025-06-02 and requires 2 weeks

-- Eksterne udviklingsforløb --

[EDI Portal udvikling API] starts on 2025-06-01 and requires 5 weeks
[EDI Portal udvikling UX] starts at [EDI Portal udvikling API]'s end and requires 6 weeks
[EDI Portal udvikling UX] starts after [Sommerferie]'s end

[Sundhed.dk DDTV UX] starts on 2025-05-01 and requires 6 weeks
[Sundhed.dk udvikling og intern test]  starts at [Sundhed.dk DDTV UX]'s end and requires 14 weeks

[DigPost i Test1] happens on 2025-07-01

[DigPost i Test2] happens on 2025-09-01

-- Udviklingsforløb --
[Udvikling Kickoff] happens on 2025-04-30
[NSP OIO-IDWS service] starts 2 days after [Udvikling Kickoff]'s end and requires 6 weeks
[QA1] happens 2 weeks after [Udvikling Kickoff]'s end
[QA2] happens 2 weeks after [QA1]'s end
[QA3] happens 2 weeks after [QA2]'s end
[QA2] displays on same row as [QA1]
[QA3] displays on same row as [QA1]

[NSP DGWS service] starts at [NSP OIO-IDWS service]'s end and requires 4 weeks
[QA4] happens at [NSP DGWS service]'s start
[QA5] happens 2 weeks after [QA4]'s end
[QA6] happens 2 weeks after [QA5]'s end
[QA5] displays on same row as [QA4]
[QA6] displays on same row as [QA4]

[NSP Job udvikling] starts at [NSP OIO-IDWS service]'s end and requires 8 weeks
[QA7] happens at [NSP Job udvikling]'s start
[QA8] happens 2 weeks after [QA7]'s end
[QA9] happens 2 weeks after [QA8]'s end
[QA10] happens on 2025-08-13
[QA11] happens on 2025-08-27

[QA8] displays on same row as [QA7]
[QA9] displays on same row as [QA7]
[QA10] displays on same row as [QA7]
[QA11] displays on same row as [QA7]

-- QA Forløb --

[Final QA (OIO-IDWS service)] starts on 2025-08-18 and requires 2 weeks
[Final QA (DGWS)] starts on 2025-08-18 and requires 2 weeks
[Final QA (Jobs)] requires 2 weeks
[Final QA (Jobs)] starts after [NSP Job udvikling]'s end and requires 2 weeks
[Option: Performancetest] starts after [Efterårsferie]'s end and requires 2 weeks

-- Tilgængelighed i NSP test --

[OIO-IDWS service på Test1] happens on 2025-07-11
[OIO-IDWS service på Test2] happens 1 weeks after [Final QA (OIO-IDWS service)]'s end

[DGWS service på Test1] happens on 2025-08-01
[DGWS service på Test2] happens 1 weeks after [Final QA (DGWS)]'s end

[Jobs på Test1] happens 2 1 weeks after [Final QA (Jobs)QA11]'s end
[Jobs på Test2] happens 2 1 weeks after [Final QA (Jobs på Test1)]'s end
[Jobs på Test1] -> [Jobs på Test2]

-- End-2-End Test --

[End-2-End test planlægning] starts on 2025-09-01 and requires 3 weeks
[End-2-End test] starts 1 days after [Jobs på Test2]'s end and requires 1 week
[End-2-End test planlægning] -> [End-2-End test]
[Jobs på Test2] -> [End-2-End test]
[EDI Portal udvikling UX] -> [End-2-End test]
[Sundhed.dk udvikling og intern test] -> [End-2-End test]

-- Drift og Ibrugtagning --
[DDTV produktionsigangsætning] starts 4 weeks after [Jobs på Test2]'s end and requires 3 weeks
[DDTV klar til ibrugtagning] happens 1 week after [DDTV produktionsigangsætning]'s end
@endgantt


...