@startgantt
Project starts 2025-03-01 printscale weekly
2025-04-14 to 2025-04-21 is closed 2025-04-14 to 2025-04-21 are named [Påske]
2025-04-14 to 2025-04-21 are colored in salmon 2025-07-14 to 2025-08-03 is closed 2025-07-14 to 2025-08-03 are named [Sommerferie] 2025-07-14 to 2025-08-03 are colored in salmon
[Research og Specifikation] as [RD] requires 6 weeks [Arkitektur Kickoff] as [M1] happens on 2025-04-03 [Udvikling Kickoff] as [M2] happens on 2025-04-28 [DDTV NSP Service udvikling] as [Sprint12] requires 8 weeks [RDM2] -> [Sprint12] [DDTV Kø udvikling] as [Q] requires 4 weeks [Q] starts 2 weeks after [Sprint12]'s start [DDTV Webserver udvikling] as [WS] requires 4 weeks [Q] -> [WS]
@endgantt