@startgantt
Project starts 2025-03-01 printscale weekly
2025-04-14 to 2025-04-21 is closed 2025-04-14 to 2025-04-21 are named [Påske]
2025-04-14 to 2025-04-21 are colored in salmon 2025-07-14 to 2025-08-03 is closed 2025-07-14 to 2025-08-03 are named [Sommerferie]
[Research og Specifikation] as [R&D] requires 8 weeks [DDTV NSP Service udvikling] as [Sprint1+2] requires 8 weeks [Sprint1+2] starts at [R&D] end [DDTV Kø udvikling] requires 4 weeks [Research og Specifikation] end [DDTV Kø udvikling] starts at [DDTV Webserver udvikling] requires 4 weeks
@endgantt