PlantUML Render Macro
@startgantt
Project starts 2025-03-01
printscale weekly
2025-04-14 to 2025-04-21 is closed
2025-04-14 to 2025-04-21 are named [Påske] 2025-04-14 to 2025-04-21 are colored in salmon
2025-07-14 to 2025-08-03 is closed
2025-07-14 to 2025-08-03 are named [Sommerferie]
[Research og Specifikation] as [R&D] requires 8 weeks
[DDTV NSP Service udvikling] as [Sprint1+2] requires 8 weeks
[Sprint1+2] starts at [R&D] end
[DDTV Kø udvikling] requires 4 weeks [Research og Specifikation] end
[DDTV Kø udvikling] starts at
[DDTV Webserver udvikling] requires 4 weeks @endgantt

...