@startgantt

<style>
ganttDiagram {
  task {
    BackGroundColor #72BEDB
    LineColor #275F78 
    unstarted {
      BackGroundColor #FA8C6E 
      LineColor #FFAF69
    }
  }
}
</style>

' Can be daily, weekly, monthly, quartley, yearly
ganttscale weekly

'saturdays are closed
'sunday are closed

2023-12-28 to 2023/12/31 is closed
'2024/02/11 to 2024/02/18 is closed
2024/04/28 to 2024/05/1 is closed

'title Identitesslørings Gantt diagram

Project starts 2023-12-28


mainframe **IDSAS projektet for SDS**

'Milestones
[End-to-end intern test] happens 2024-02-5
[End-to-end ekstern test] happens 2024-02-21
[End-to-end ekstern test] is colored in #d20500
[Lovgivning træder i kraft] happens 2024-03-1


'[Afdelingssløring muligvis impementeret i først halvår 2024 ?] happens 2024-06-30

[SDK monolit release?] happens 2024-03-12 

[ ] ends 2024-06-01

 --IDSAS 1.0.3  --

[IDSAS 1.0.3 Udv] starts 2024/1/25
[IDSAS 1.0.3 Udv] lasts 3 days
[IDSAS 1.0.3 Udv] is 100% completed 

[IDSAS 1.0.3 QA] starts 2024/1/25
[IDSAS 1.0.3 QA] lasts 1 days
[IDSAS 1.0.3 QA] is 100% completed

[IDSAS 1.0.3 TEST1] starts 2024/1/26 
[IDSAS 1.0.3 TEST1] is 22% completed  
[IDSAS 1.0.3 TEST1] lasts 140 days
[IDSAS 1.0.3 TEST2] starts 2024/2/2 
 [IDSAS 1.0.3 TEST2] is 18% completed    

[IDSAS 1.0.3 TEST2] lasts 140 days 
[IDSAS 1.0.3 Prod] happens at 2024/3/1
[IDSAS 1.0.3 Prod] is colored in #d20500
 




-- STS --

[STS Udvikling] starts 2024/1/1
[STS Udvikling] lasts 25 days  
[STS Udvikling] is 100% completed
[STS QA] starts 2024/1/3
[STS QA] lasts 23 days  
[STS QA] is 100% completed

[STS TEST1] starts 2024/1/26 
[STS QA] is 100% completed
[STS TEST1] lasts 140 days 
[STS TEST2] starts 2024/2/5
[STS TEST2] lasts 140 days

[STS Prod] happens at 2024/3/4
[STS Prod] is colored in #d20500
[STS TEST1] is 22% completed
[STS TEST2] is 14% completed

'[STS Performances test] starts 2024/02/18
'[STS Performances test] lasts 10 days 
'[STS Performances test] is Colored in red


-- MinLog2 --

[MinLog udv] starts 2024/1/1



[MinLog udv] lasts 34 days 
[MinLog QA] lasts 3 days 
[MinLog QA] starts 2024/02/05
[MinLog TEST1] starts 2024/02/06
[MinLog TEST1] lasts 140 days 
[MinLog TEST1] is 18%12% completed

[MinLog TEST2] starts 2024/02/12
[MinLog TEST2] lasts 140 days
[MinLog TEST2] is 12%10% completed

[MinLog Prod] happens at 2024/03/04
'[MinLog Prod] las
[MinLog Prod] is colored in #d20500


[MinLog udv] is 100% completed
[MinLog QA] is 100% completed


@endgantt

...