PlantUML Macro
@startgantt

<style>
ganttDiagram {
  task {
    BackGroundColor #72BEDB
    LineColor #275F78 
    unstarted {
      BackGroundColor #FA8C6E 
      LineColor #FFAF69
    }
  }
}
</style>

' Can be daily, weekly, monthly, quartley, yearly
ganttscale weekly

'saturdays are closed
'sunday are closed

2023-12-28 to 2023/12/31 is closed
2024/02/11 to 2024/02/18 is closed
2024/04/28 to 2024/05/1 is closed

'title Identitesslørings Gantt diagram

Project starts 2023-12-28


mainframe **IDSAS projektet for SDS**

'Milestones
[End-to-end intern test] happens 2024-01-31
[End-to-end ekstern test] happens 2024-02-21
[End-to-end ekstern test] is colored in #d20500
[Lovgivning træder i kraft] happens 2024-03-1


'[Afdelingssløring muligvis impementeret i først halvår 2024 ?] happens 2024-06-30

[SDK monolit release?] happens 2024-03-12 

[ ] ends 2024-06-01


-- IDSAS --
'[IDSAS 1,0 QA] starts 2023/12/1

'[IDSAS 1,0 QA] lasts 14 days

'[IDSAS 1,0 TEST1] starts 2024/1/1

'[IDSAS 1,0 TEST1] is 100% completed

[IDSAS 1,0 TEST2] starts 2024/1/4

[IDSAS 1,0 TEST2] is 70% completed

'[IDSAS 1,0 TEST1] lasts 23 days
[IDSAS 1,0 TEST2] lasts 22 days 
'then [IDSAS 1,0 Prod] 'happens at [IDSAS 1,0 'TEST2]'s end
'[IDSAS 1,0 Prod] is 'colored in #5A5A5A


--IDSAS 1.0.1.1  --

'[IDSAS 1.0.1 def] starts 2023/12/11
'[IDSAS 1.0.1 def] lasts 10 days
'[IDSAS 1.0.1 def] is 100% completed

[IDSAS 1.0.1 Udv] starts 2024/1/1
[IDSAS 1.0.1 Udv] lasts 10 days
[IDSAS 1.0.1 Udv] is 100% completed 

[IDSAS 1.0.1 QA] starts 2024/1/12
[IDSAS 1.0.1 QA] lasts 2 days
[IDSAS 1.0.1 QA] is 100% completed

[IDSAS 1.0.1 TEST1] starts 2024/1/18 
[IDSAS 1.0.1 TEST1] is 20% completed  
[IDSAS 1.0.1 TEST1] lasts 26 days
[IDSAS 1.0.1 TEST2] starts 2024/1/19  
[IDSAS 1.0.1 TEST2] lasts 14 days 
then [IDSAS 1.0.1 Prod] happens at [IDSAS 1.0.1 TEST2]'s end 
[IDSAS 1.0.1 Prod] is colored in #d20500
 [IDSAS 1.0.1 TEST2] is 0% completed   


' Completion status can be can be set with "is XX% compeleted"
'[IDSAS QA] is 45% completed

'[IDSAS TEST1] starts 2023/12/13

'--IDSAS 1,2  Kafka ? --

'[CVR Def] starts 2024/1/30
'[CVR Def] lasts 20 days
'then [CVR Udv] lasts 35 days 
'then [CVR QA] lasts 14 days
'then [CVR TEST1] lasts 14 days
'then [CVR TEST2] lasts 14 days 
'then [CVR Prod] happens at [CVR TEST2]'s end 
'[CVR Prod] is colored in #5A5A5A


' Completion status can be can be set with "is XX% compeleted"
'[IDSAS QA] is 45% completed

'[IDSAS TEST1] starts 2023/12/13

-- STS --

[STS Udvikling] starts 2024/1/1
[STS Udvikling] lasts 1825 days  
[STS Udvikling] is 100% completed
[STS QA] starts 2024/1/3
[STS QA] lasts 1620 days  
[STS QA] is 100% completed

[STS TEST1] starts 2024/1/1925 

then [STS TEST1] lasts 14 days 
then [STS TEST2] lasts 14 days
then [STS Prod] happens at [STS TEST2]'s end 
[STS Prod] is colored in #d20500
[STS TEST1] is 0% completed


'[STS Performances test] starts 2024/02/18
'[STS Performances test] lasts 10 days 
'[STS Performances test] is Colored in red


-- MinLog2 --

[MinLog udv] starts 2024/1/1



[MinLog udv] lasts 2025 days
then [MinLog QA] lasts 7 days 
then [MinLog TEST1] lasts 14 days 
then [MinLog TEST2] lasts 14 days
then [MinLog Prod] happens at [MinLog TEST2]'s end 
[MinLog Prod] is colored in #d20500


[MinLog udv] is 85% completed



@endgantt

...

Forventet/ ca. datokomponent

Test1

Test2

Produktion
















Ultimo januar 2024MinLog LookupID med IDSAS understøttelse TEST1

Medio januar 2024Identitestsløringsservice v. 1.0.1.118. januar 2024

Medio januar 2024STS med IDSAS understøttelse borgerspecifik sløring 2.8.3X39TEST1

December 2023Identitestsløringsservice v. 1.0.014. december 2023

5. januar 2024


NovemberRC frigivet - Identitestsløringsservice 1.0.0 - rc.813. november 2023

AugustFørste RC frigivet - Identitestsløringsservice 1.0.0 - rc.622. august 2023

  1. marts 2023
Udvikling af komponenter til oprettelse af sløring mm.-

  1. juni 2022
Identitessløringsprojektet i gang sat-

...