@startgantt
<style>
ganttDiagram {
task {
BackGroundColor #72BEDB
LineColor #275F78
unstarted {
BackGroundColor #FA8C6E
LineColor #FFAF69
}
}
}
</style>
' Can be daily, weekly, monthly, quartley, yearly
ganttscale weekly
'saturdays are closed
'sunday are closed
2023/12/22 to 2024/01/1 is closed
2024/02/11 to 2024/02/18 is closed
'title Identitesslørings Gantt diagram
Project starts 20232024-121-1
mainframe **IDSAS projektet for SDS**
'Milestones
[End-to-end intern test] happens 2024-01-31
[End-to-end ekstern test] happens 2024-02-21
[End-to-end ekstern test] is colored in #d20500
[Lovgivning træder i kraft] happens 2024-03-1
'[Afdelingssløring muligvis impementeret i først halvår 2024 ?] happens 2024-06-30
[SDK monolit release?] happens 2024-03-12
[ ] ends 2024-06-01
-- IDSAS --
'[IDSAS 1,0 QA] starts 2023/12/1
'[IDSAS 1,0 QA] lasts 14 days
[IDSAS 1,0 TEST1] starts 20232024/121/141
[IDSAS 1,0 TEST1] is 100% completed
[IDSAS 1,0 TEST2] starts 2024/1/4
[IDSAS 1,0 TEST2] is 70% completed
[IDSAS 1,0 TEST1] lasts 23 days
then [IDSAS 1,0 TEST2] lasts 16 days
'then [IDSAS 1,0 Prod] 'happens at [IDSAS 1,0 'TEST2]'s end
'[IDSAS 1,0 Prod] is 'colored in #5A5A5A
--IDSAS 1.0.1.1 --
'[IDSAS 1.0.1 def] starts 2023/12/11
'[IDSAS 1.0.1 def] lasts 10 days
'[IDSAS 1.0.1 def] is 100% completed
[IDSAS 1.0.1 Udv] starts 2024/1/1
[IDSAS 1.0.1 Udv] lasts 10 days
[IDSAS 1.0.1 Udv] is 100% completed
[IDSAS 1.0.1 QA] starts 2024/1/12
[IDSAS 1.0.1 QA] lasts 2 days
[IDSAS 1.0.1 QA] is 100% completed
[IDSAS 1.0.1 TEST1] starts 2024/1/18
[IDSAS 1.0.1 TEST1] lasts 2 days
then [IDSAS 1.0.1 TEST2] lasts 14 days
then [IDSAS 1.0.1 Prod] happens at [IDSAS 1.0.1 TEST2]'s end
[IDSAS 1.0.1 Prod] is colored in #d20500
' Completion status can be can be set with "is XX% compeleted"
'[IDSAS QA] is 45% completed
'[IDSAS TEST1] starts 2023/12/13
'--IDSAS 1,2 CVR def og Kafka ? --
'[CVR Def] starts 2024/1/30
'[CVR Def] lasts 20 days
'then [CVR Udv] lasts 35 days
'then [CVR QA] lasts 14 days
'then [CVR TEST1] lasts 14 days
'then [CVR TEST2] lasts 14 days
'then [CVR Prod] happens at [CVR TEST2]'s end
'[CVR Prod] is colored in #5A5A5A
' Completion status can be can be set with "is XX% compeleted"
'[IDSAS QA] is 45% completed
'[IDSAS TEST1] starts 2023/12/13
-- STS --
[STS Udvikling] starts 20232024/121/6
1
[STS Udvikling] lasts 18 days
[STS Udvikling] is 95% completed
[STS QA] starts 2024/1/3
[STS QA] lasts is16 days 85% completed
[STS UdviklingQA] lastsis 3285% days completed
then [STS QATEST1] lasts 16 days starts 2024/1/19
then [STS TEST1] lasts 14 days
then [STS TEST2] lasts 14 days
then [STS Prod] happens at [STS TEST2]'s end
[STS Prod] is colored in #d20500
'[STS Performances test] starts 2024/02/18
'[STS Performances test] lasts 10 days
'[STS Performances test] is Colored in red
-- MinLog2 --
[MinLog udv] starts 2023/12/12
[MinLog udv] lasts 27 days
then [MinLog QA] lasts 7 days
then [MinLog TEST1] lasts 14 days
then [MinLog TEST2] lasts 14 days
then [MinLog Prod] happens at [MinLog TEST2]'s end
[MinLog Prod] is colored in #d20500
[MinLog udv] is 85% completed
@endgantt
|
...